Saturday, February 19, 2011

ROOFING the DORMITORY

Soil completing the foundations


With the foundations only days away from being finished, it is time for Big John to start fine-tuning the later stages of construction.   From the first set of photos you can see brick walls demarcating each room but now these sections are filled with soil for workers to then lay the concrete, therein completing the foundations.  









Engineer Toni is in charge of paying his labourers and managing the site, while it is Big John who"shops around" to source all the materials.  Yesterday we met with the roofing specialist from a large company in Jinja on site who provided us with this quote:

Provisional Roofing Budget

Item
Quantity
                                
Unit cost
 Total spent  
     (UGshs)                
Timber 4x2
330
5000
1,650,000
Timber 3x2
230
4000
920,000
Timber 8x1
70
15,000
1,050,000
Timber 6x2
70
10,000
700,000
Timber 4x3
37
10,000
370,000
Timber 6x2
70
10,000
700,000
Iron Sheets
280
50,000
14,000,000
Riges
50
20,000
1,000,000
Valley
                         7
20,000
140,000
Nails 6
30
4,500
135,000
Nails 4
40
4,500
160,000
Nails 3
25
4,500
112,500
Nails 2.5
15
4,500
67,500
Nails 1.5
40
4,500
180,000
Roofing Nails
50 kg
4,500
225,000
Plastic Cover
6 packets
20,000
120,000
Hop Iron
4
35,000
140,000
Labor


1,000,000







22,670,000

USD $9,857